I have put a short video of the start of the screed pour at the end of this blog entry, so if you are the impatient sort, you can jump right there!
To say I was having
kittens this morning is an understatement: there were so many ways
today's screeding of the kitchen wing floor could go wrong.
I had followed the
company's guidelines on arranging the sub-floor construction for a
minimum screed depth of 50mm. However, I discovered on the company's
costing spreadsheet just last night that they were only going to
supply 40 mm! Their area estimate of 111 m2 gave in consequence
their volume estimate of 4.4 m3. The company were only bringing 4.75
m3, so their tolerances were already very tight.
In last night's
panic I did my own calculations using multiple depth measurements to
get an average screed depth for each room. The kitchen in particular
introduces huge uncertainty as the floor height is all over the place
because it is above basement vaulting. The sub-floors of all the
other rooms in the kitchen wing were installed at different depths so
nothing was standard. This was despite me emailing plans to try to
ensure consistency! :-) Anyhow, my own calculations gave a figure of
4.5 m3, and I breathed a sigh of relief as I was in the company's
window. However, I had a niggling doubt that the screeding would run
out because of the previously mentioned discrepancy, and dashed off
an email to the company about the inconsistent depths in their
documentation. I hoped this would cover my back.
Gregor and Andrew
arrived early to hold my hand, which was very kind of them. However,
when the workmen arrived from the screeding company, Andrew and
Gregor headed off to do some landscape gardening in the grounds of
the castle. No-one else wanted to take responsibility for the
screeding so I had to be on site myself. Indeed supervising the
screeding was the principal reason for my current stay at the castle,
and I had known for years that no-one else wanted to do it. This is
as it should be of course – I was paying the money – but it
didn't make it any less nerve-racking.
I showed the workmen
the room layout, the finished level I wanted and explained the
existing irregularities in levels e.g. stone slabs at opposite ends
of rooms which you would assume were at the same level, were out by
up to 13mm. I even started miming with a slate tile, assuming that
gesture and show would remove any ambiguity in what I was saying. One
of the workmen must have picked-up my nervousness, as he said “We
do this every day, we know what we are doing.”. I had no doubt they
knew what they were doing, but was concerned they were doing it with
my money :-) and that I had not communicated properly the
non-standard requirements of the castle's restoration.
Before any pouring,
the workmen placed a large number of small metal tripods in each
room. Using a laser level the workmen screwed down a circular plate
built into the tripod, to the final floor level. The pour would be
complete when it reached the level of these circular plates. Using
the measurements obtained the workmen came up with a figure of 5 m3.
I was warned that, in consequence, they might need to fetch another
lorry-load of screed and that this would cost me an arm and a leg. My
panic increased!
The workmen wanted
me to tape a few bits of pipe and a few lengths of expansion strip
down to ensure they would not float during the pour. I was eager to
oblige as I just didn't want anything to go wrong. During the pour,
they said that by going just 2 millimetres lower in each room, that
they thought they could manage with 4.75 m3. I readily agreed! There
was another panic in the former scullery, as they had to go higher
than the requested floor level to ensure some pipes would be properly
covered - but would this cause the screed to run out?
So yes, I was on
hand to make some quick real-time decisions – again as it should
but my adrenalin was definitely on high! My mouth was going dry, and
when your body responds, you know you are giving birth to kittens.
:-)
There was a hump in
one part of the kitchen floor, isolating a low area which I had
identified as problematic. One of the workmen found this and asked if
I wanted him to kick some screed in there. My response: “Yes,
please!”
At one stage, I
could see some pipes in the kitchen rising slightly above the surface
of the screed. This is called “crowning” and I was trying to
assess how bad it would be. However, the workmen do a second pass
where they spray the screed with a hardener and tamp the surface with
a T-shaped tool. Thankfully the crowning disappeared after this.
The whole pour only
took about 30 minutes – much quicker than the preparations and
indeed much quicker than the subsequent cleaning up. As the pumping
finished in the last room with the workmen running out of screed, it
looked to a first approximation that there had just been enough
screed and that the levels were about right. I deliberately did not
look too closely as what had been done was now a fait-accompli and I
could check things over accurately once the screed had dried. I was
too worried about falling into the liquid screed, and spoiling the
good judgement and care which had accompanied the pour.
I was
asked if they could pump out the remaining contents of the wide bore
pipe on the grass. I asked “Well how much is in there?” as I
didn't want to pollute the castle grounds. It turned out there would
be quite a lot, so I asked if they could fill some containers instead
and I could use this to fill voids in the entrance hall floor. We had
cleared out the entrance hall just in case there was any remaining
screed. In the end we managed to get a couple of full barrow loads on
the entrance hall floor. This was some last minute running around I
was not expecting – and yes I was panicing! :-)
The most important
thing, I guess, is that the membrane Andrew installed did not leak –
hurrah! We had gone round this a number of times taping any holes or
places where leaks might occur.
In fact the
screeding is such a major and long anticipated landmark that I cannot
believe it has actually happened. Acceptance may take some time,
perhaps after 48 hours when one can actually walk on it? I will do another blog entry with the "after pour" pictures.
Huge thanks to Danny
and Norbert of East-West Flooring for bringing their professional and
good-humoured charm to a stressed-out castle laird!
kitchen tripod invasion |
scullery tripod invasion |
pantry tripod invasion |
bowser from front |
bowser from rear |
bowser from side |
Danny (bucket) and Norbert (hose) in action
I felt sick for you while reading this! Glad it's worked out in the end
ReplyDelete